Library Technology Team
Projects Schedule: Acorn Replacement
Unicorn Hardware Replacement
DescriptionWho?Planned
Begin date
Estimated
Time
Planned
Completion date
Actual
Completion Date
Select Vendor and Equipment Marshall, Maryanne, Theo April 1, 1997 16 hours April 15, 1997 April 15, 1997
Order Equipment Pat, Marshall, Flo May 1, 1997 1 hours Upon Provost approval May 9, 1997
Plan Unicorn Conversion SIRSI, Maryanne Jun 30, 1997 20 hours Jun 30, 1997 Jun 30, 1997
Hardware Installation Decision One, SUN June 30, 1997 10 hours Jul 3, 1997 Jun 25, 1997
Solaris Installation ACIS TI, Maryanne July 3, 1997 10 hours Jul 7, 1997 Jun 30 1997
Transfer Unicorn Software/Data (trial run) SIRSI, Maryanne, Ramona July 7, 1997 5 hours Jul 11, 1997 Jul 8, 1997
Rebuild Indexes (trial run) SIRSI, Maryanne, Ramona July 11, 1997 48 hours Jul 14, 1997 Jul 11, 1997
Transfer Unicorn Software/Data (Final run) SIRSI, Maryanne, Ramona July 14, 1997 5 hours Jul 18, 1997 Jul 18, 1997
Rebuild Indexes (Final run) SIRSI, Maryanne, Ramona July 18, 1997 48 hours Jul 20, 1997 Jul 20, 1997
Transfer Production Server Ramona, Maryanne Jul 21, 1997 8 hours Jul 21, 1997 Jul 21, 1997