| Unicorn Hardware Replacement | |||||
| Description | Who? | Planned Begin date | Estimated Time | Planned Completion date | Actual Completion Date |
|---|---|---|---|---|---|
| Select Vendor and Equipment | Marshall, Maryanne, Theo | April 1, 1997 | 16 hours | April 15, 1997 | April 15, 1997 |
| Order Equipment | Pat, Marshall, Flo | May 1, 1997 | 1 hours | Upon Provost approval | May 9, 1997 |
| Plan Unicorn Conversion | SIRSI, Maryanne | Jun 30, 1997 | 20 hours | Jun 30, 1997 | Jun 30, 1997 |
| Hardware Installation | Decision One, SUN | June 30, 1997 | 10 hours | Jul 3, 1997 | Jun 25, 1997 |
| Solaris Installation | ACIS TI, Maryanne | July 3, 1997 | 10 hours | Jul 7, 1997 | Jun 30 1997 |
| Transfer Unicorn Software/Data (trial run) | SIRSI, Maryanne, Ramona | July 7, 1997 | 5 hours | Jul 11, 1997 | Jul 8, 1997 |
| Rebuild Indexes (trial run) | SIRSI, Maryanne, Ramona | July 11, 1997 | 48 hours | Jul 14, 1997 | Jul 11, 1997 |
| Transfer Unicorn Software/Data (Final run) | SIRSI, Maryanne, Ramona | July 14, 1997 | 5 hours | Jul 18, 1997 | Jul 18, 1997 |
| Rebuild Indexes (Final run) | SIRSI, Maryanne, Ramona | July 18, 1997 | 48 hours | Jul 20, 1997 | Jul 20, 1997 |
| Transfer Production Server | Ramona, Maryanne | Jul 21, 1997 | 8 hours | Jul 21, 1997 | Jul 21, 1997 |
| Vanderbilt University | Heard Library StaffWeb | Library Technology |