Upgrades to Central / Science Public Stations

This project involves the migration of the public-access workstations in the Central / Science & Engineering Libraries to a new operating environment. The previous environment included Windows 3.x, a user interface created through Saber Menu, and a CD-ROM server based on LanCD/FastCD. The new environment will use Windows NT as the operating environment, Netscape Navigator as the primary user interface, and will use a Novell IntranetWare 4.11 server for CD-ROM applications. The CD-ROM discs for the Central/Science will reside on either magnetic drives of the IntranetWare server or will be managed through the 150-disc NSM Mercury 40 Jukebox.

Central/Science Public Workstation Upgrades
DescriptionWho?Planned
Begin date
Estimated
Time
Planned
Completion date
Actual
Completion Date
Prepare LIBRARY7 CD-ROM Server Marshall Jul 15, 1997 2 weeks Aug 1, 1997 Aug 20, 1997
Upgrade all workstations to 32MB Memory Jody, John, Susan July 15, 1997 1 week Aug 1, 1997 .
Convert workstation: CPACL_0 (Pillar) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CPACL_1 (Alcove cluster) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CPACL_2 (Alcove cluster) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CPACL_3 (Alcove cluster) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CPACL_4 (Alcove cluster) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CPACL_5 (Alcove cluster) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CPACL_6 (Alcove cluster) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CPACL_7 (Alcove cluster) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CPACL_8 (Alcove cluster) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CPACL_9 (Alcove cluster) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997; subsequent hd failure/machine repair needed 9/15
Convert workstation: CPACL_10 (Alcove cluster) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CPACL_11 (Alcove cluster) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CREFPAC1 (Reference Room) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CREFPAC2 (Reference Room) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CREFPAC3 (Reference Room) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997, subsequent hd failure--replaced on 9/15; 1st phase NT intallation started 9/16 a.m.
Convert workstation: CREFPAC4 (Reference Room) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CREFPAC5 (Reference Room) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CREFPAC6 (Reference Room) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CREFPAC7 (Reference Room) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CREFPAC8 (Reference Room) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CENREF9 (Reference Room) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: CENREF10 (Reference Room) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: SCIPAC0 (Science Reference Area) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: SCIPAC1 (Science Reference Area) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: SCIPAC2 (Science Reference Area) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: SCIPAC3 (Science Reference Area) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: SCIPAC4 (Science Reference Area) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: SCIPAC5 (Science Reference Area) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: SCIPAC6 (Science Reference Area) Jody, Marshall Aug 1, 1997 0.5 hr Aug 15, 1997 Aug 23, 1997
Convert workstation: GOVDOC1 (Government Documents) Jody Aug 1, 1997 0.5 hr Aug 15, 1997 Sep 10, 1997 (web interface installed)
Convert workstation: GOVDOC2 (Government Documents) Jody Aug 1, 1997 0.5 hr Aug 15, 1997 harddrive failure/cmos corruption 9/10; hd replacement 9/15; Completed Sep 16, 1997
Convert workstation: CENCLASS (Central Classroom) Jody Aug 1, 1997 0.5 hr Sep 8, 1997 Sep 8, 1997 (web interface)
Convert workstation: SCICLASS (Science Classroom) Jody Aug 1, 1997 0.5 hr Aug 15, 1997 available station id'ed 9/12
Convert workstation: CREADRM8 (Arts Classroom) Jody Aug 1, 1997 0.5 hr Aug 15, 1997 harddrive+floppy failure (replace station--9/12); 1st phase NT installation restarted 9/16 a.m. completed 9/16 p.m.
Convert workstation: SYS_CLASS1 (Training Room) Jody Aug 1, 1997 0.5 hr Aug 15, 1997 Sep 5, 1997
Convert workstation: SYS_CLASS2 (Training Room) Jody Aug 1, 1997 0.5 hr Aug 15, 1997 Sep 5, 1997
Convert workstation: SYS_CLASS3 (Training Room) Jody Aug 1, 1997 0.5 hr Aug 15, 1997 Sep 5, 1997
Convert workstation: SYS_CLASS4 (Training Room) Jody Aug 1, 1997 0.5 hr Aug 15, 1997 Sep 5, 1997
Convert workstation: SYS_CLASS5 (Training Room) Jody Aug 1, 1997 0.5 hr Aug 15, 1997 Sep 5, 1997
Convert workstation: SYS_CLASS6 (Training Room) Jody Aug 1, 1997 0.5 hr Aug 15, 1997 Sep 5, 1997
Convert workstation: CSTACK5 (5th Level by Elevator) Jody Aug 1, 1997 0.5 hr Aug 15, 1997 ?
Convert workstation: CSTACK6 (6th Level by Elevator) Jody Aug 1, 1997 0.5 hr Aug 15, 1997 ?
Convert workstation: CPER6 (6th Level Reading Room) Jody Aug 1, 1997 0.5 hr Aug 15, 1997 ?
Convert workstation: CSTACK7 (7th Level by Elevator) Jody Aug 1, 1997 0.5 hr Aug 15, 1997 ?
Convert workstation: CSTACK8 (8th Level by Elevator) Jody Aug 1, 1997 0.5 hr Aug 15, 1997 ?