Friday December 28th
8:00pm The last libraries (Biomedical and
Science and Engineering) close.
8:00pm-11:00pm Refresh copy of ACORN that
will be used while production ACORN is being upgraded. ACORN
will not be available to patrons or staff for these three hours.
11:00pm ACORN will be available for
limited use*.
11:05pm start upgrade
12:00am start rebuild headings
Saturday December 29th:
4:00pm Start Rebuild Authorities
7:00pm Start Authority maintainence
Sunday December 30th
7:00am Start Rebuildtext
10:00pm Start Rebuild thesauri
Monday December 31st
2:00am: Run correct thesauri
3:00am: Run correct thesauri
4:00am: Run correct thesauri
6:00am: Switch back to Production ACORN and
continue to run correct thesauri. Full use of ACORN can resume.
*No editing of bibliographic
records. Circulation OK.